Formula
1)
Critical Ratio
(CR) = Actual Time Remaining
Lead time
remaining
2)
Actual Time
Remaining = Due date – present date
CR < 1 (Actual time < Lead time) = Order is BEHIND schedule CR = 1 ( Actual time = Lead time ) = Order is ON schedule CR > 1 ( Actual time > Lead time ) = Order is AHEAD schedule CR = 0/- ( Today date> Due date) = Order is ALREADY LATE |
Example Problem
1. An
order for 500 of buns is processed on machine 001 and 002. The set up time on
001 is 30 minutes, and the run time is 2 minutes per unit. The set up time on
002 is 20 minutes, and the run time is 5 minutes per units. Wait time between
the two operations is 50 minutes. The move time between 001 and 002 is 4
minutes. Wait time after operation 002 is 50 minutes, and the move time into
stores is 7 minutes. There is no queue at either workstation. Calculate the
total manufacturing lead time for the order.
001 002
Setup
time 30 minutes 20
minutes
Run
time 2 minutes 5
minutes
Wait
time 50 minutes 50
minutes
Move
time 4 minutes 7
minutes
Solution:
Work center 001 operation time = 30 + (500 x
2) = 1030 minutes
Wait
time =
50 minutes
Move
time = 4 minutes
Work
center 002 operation time = 20 + (500 x 5) = 2520 minutes
Wait
time = 50 minutes
Move
time = 7 minutes
Total
Manufacturing lead time =
3661 minutes
=
61 hours 1 minute
2. An order for 400 of product is processed on work center 111 and 222. The set up time on 111 is 20 minutes, and the run time is 10 minutes per piece. The set up time on 222 is 40 minutes, and the run time is 20 minutes per piece. Wait time between the two operations is 4 hours. The move time between 111 and 222 is 2 hours. Wait time after operation 222 is 2 hours, and the move time into stores is 25 minutes. There is a queue at work center 111 is 15 hours and at 222 is 20 hours. Calculate the total manufacturing lead time for the order.
2. An order for 400 of product is processed on work center 111 and 222. The set up time on 111 is 20 minutes, and the run time is 10 minutes per piece. The set up time on 222 is 40 minutes, and the run time is 20 minutes per piece. Wait time between the two operations is 4 hours. The move time between 111 and 222 is 2 hours. Wait time after operation 222 is 2 hours, and the move time into stores is 25 minutes. There is a queue at work center 111 is 15 hours and at 222 is 20 hours. Calculate the total manufacturing lead time for the order.
111 222
Set
up time 20
minutes 40
minutes
Run
time 10
minutes 20
minutes
Wait time 4
hours 2
hours
Move time 2
hours 25
minutes
Queue time 15
hours 20
hours
Solution:
Work center 111
operation time = 20 + (400 x 10) = 4020 minutes
Wait time = 4 hours x 60 = 240 minutes
Move time = 2 hours x 60 = 120 minutes
Queue time = 15 hours x 60 = 900 minutes
Work center 222
operation time = 40 + (400 x 20) = 8040 minutes
Wait time = 2 hours x 60 = 120 minutes
Move time
= 25 minutes
Queue time = 20 hours x 60 = 1200 minutes
Total
manufacturing lead time = 14 665 minutes
= 244 hours 25 minutes
3. If
today is manufacturing day 100 and an order has a due date of 120 and a lead
time remaining of 25 days, the critical ratio would be?
Solution:
Critical
ratio = Due date – present date
Lead time remaining
= 120 – 100
25
= 0.8
Ø CR < 1 (actual time < lead time) = order is behind schedule.
4. If
today is manufacturing day 100 and an order has a due date of 120 and a lead
time remaining of 12 days, the critical ratio would be?
Solution:
Critical
ratio = Due date – present date
Lead time remaining
= 120 – 100
12
= 1.67
Ø CR > 1 (actual time > lead time) = order is ahead schedule.
5. If
today is manufacturing day 100 and an order has a due date of 125 and a lead
time remaining of 25 days, the critical ratio would be?
Solution:
Critical
ratio = Due date – present date
Lead time remaining
= 125 – 100
25
= 1
Ø CR = 1 ( actual time = lead time) = order on schedule.